Please click here to see rendering of the Waterford High School addition updated February 2011.Please click here to see a pdf presentation showing the current progress of the WHS construction presented to the BOE on September 22, 2011 by Jay Miner, Director of Buildings & Grounds.
Click here to see a pdf layout of the new Media Center and Main Office suite. (September 2011)
Click here to see a pdf presentation of the revised renovation scope of the new Waterford High School. (July 2011)
Site Facilities Construction Schedule (as of March 2011) Football Field: March 2011 - November 2011
Partial Baseball Field: March 2011 - September 2013
Full Baseball Field: June 2013 - September 2013
Soccer/Lacrosse Fields: Janaury 2011 - September 2013
Tennis Courts: Not impacted by construction; access to be coordinated
Practice Football Field: February 2011 - September 2013
Practice Fields by Miner Lane: June 2013 - September 2013
Track: March 2011 - September 2013
Zipline: Not to be used during construction
Under renovation and not available for use April 2012 - September 2012
Lobby, Auditorium, Vestibule, and Concessions
2nd Floor Lobby, Projection Rooms
Hallway between the Auditorium and the Band/Chorus room
Under renovation and not available for use June 2012 - September 2012
Under renovation and not available for use May 2013 - September 2013
Click here for a detailed map of the construction phasing